St Giles Circus
MSL completed the redevelopment for immersive media and entertainment business boasting the world’s largest high-resolution wrap-around screens, a new 2000 capacity live events venue. The project also included Cat A office fit-out on 7 no separate levels within newly built buildings within the complex.
We completed the install of the lighting and power supplies to the CAT A office space, Urban Galleries, Now Treading Area and the building Data Centre and all relevant circulation areas, as well as all new Mechanical ventilation, hot and cold-water services, and above ground drainage systems.
The MEPH installations to this new entertainment facility reached practical completion in May 2022 for 8 Build .
Project Highlights:
– Central Refrigerant System Inc Primary & Secondary Cooling
– Local Heating & Ventilation Systems via VRF
– All HWS/CWS Systems
– All Foul above ground drainage
– Inert Gas Fire Suppression Systems to Data Rooms
– Fully automated lighting control system.
– Electrical Containment systems installed within restricted above voids to maximise usable space.
– Install power supplies for all high-resolution screens including Hosts and all Supporting Host supplies. (In excess of 700 no individual power supplies)
– New Fire & Disabled Alarms and Refuge Alarm Systems to revised space allocation.
– Internal LED Lighting, Emergency Lighting & Lighting Control Systems